So: How Much Ready Mix Concrete Do You Really Need?
Every concrete project starts with the same question: how many cubic yards do I need to order? Whether you are pouring a driveway, setting footings for a new deck, or laying a patio slab, getting the quantity right saves you money and keeps your project on schedule.
Use EcoTerra’s free ready mix calculator below to estimate the cubic yards required for your project. Enter your dimensions, and we’ll do the math: no sign-up, no guesswork.
Pro Tip: Always add 5–10% to your calculated total to account for uneven subgrade, spillage, and slight measurement variations. Running short mid-pour is far more expensive than ordering a little extra.
Ready Mix Calculator
"*" indicates required fields
How to Measure for Concrete
Accurate measurements are the foundation of a successful pour. Here is how to measure the three most common project types:
Slabs (Patios, Driveways, Garage Floors)
Measure the length and width of the area in feet, then determine the thickness in inches. Most residential slabs are 4 inches thick for walkways and patios, or 5–6 inches for driveways and garage floors that need to support vehicle weight. Multiply length by width by thickness (converted to feet), then divide by 27 to get cubic yards.
Footings & Foundations
Footings are typically 12–24 inches wide and 6–12 inches deep, depending on local building codes and the load they need to support. Measure the total linear footage of the footing, then multiply by its width and depth (both in feet) and divide by 27.
Columns & Round Forms
For round forms like Sonotubes, measure the diameter and height in inches. The formula uses pi (π) to calculate the volume of a cylinder: multiply π by the radius squared by the height, then convert to cubic yards. Our calculator handles this automatically when you select the column shape.
Quick Reference: Common Project Sizes
|
|
|
|
||||
|---|---|---|---|---|---|---|---|
|
Sidewalk (3’ x 30’) |
3’ x 30’ |
|
~1.1 yards |
||||
|
Small Patio (10’ x 10’) |
|
4″ |
~1.25 yards |
||||
|
Large Patio (12’ x 20 |
12’ x 20’ |
4″ |
~3.0 yards |
||||
|
Single-Car Driveway (10’ x 20’) |
10’ x 20’ |
5″ |
~3.1 yards |
||||
|
Two-Car Driveway (20’ x 20’) |
20’ x 20’ |
5″ |
~6.2 yards |
||||
|
Garage Floor (20’ x 24’) |
20’ x 24’ |
6″ |
~8.9 yards |
||||
|
Shed Slab (10’ x 12’) |
10’ x 12’ |
4″ |
~1.5 yards |
Note: These estimates do not include the recommended 5–10% waste buffer. Always round up when placing your order.
What Does a Cubic Yard of Concrete Look Like?
A cubic yard of concrete is a volume of 3 feet by 3 feet by 3 feet: 27 cubic feet in total. Poured on a perfectly flat surface at 4 inches thick, one cubic yard covers approximately 81 square feet (roughly a 9’ x 9’ area). A standard ready mix truck typically carries 8–10 cubic yards per load, and a cubic yard of wet concrete weighs approximately 4,000 pounds.
For a quick mental shortcut on 4-inch slabs: divide your total square footage by 81 to get an approximate cubic yard count. Then add your waste buffer.
When to Order Ready Mix vs. Bagged Concrete
For projects under 1 cubic yard (roughly a 10’ x 10’ slab at 4 inches), bagged concrete from a hardware store can be a practical option: just keep in mind that one cubic yard requires approximately 45 bags at 80 pounds each, which is over 3,600 pounds of material to handle by hand.
For anything larger than 1 yard, ready mix delivery is almost always the better choice. It saves hours of labor, delivers consistent mix quality, and eliminates the risk of cold joints caused by staggered pours from batch mixing.
EcoTerra’s Advantage: Volumetric Mixing
Unlike traditional drum trucks that arrive with a pre-mixed load, EcoTerra’s volumetric mixers produce fresh concrete on your job site. This means you pay only for what you use: no short-load fees, no wasted material, and no pressure from the 90-minute delivery window that makes traditional ready mix a race against the clock. If your pour takes longer than expected, the concrete in our truck is still dry until you need it.
Tips for Ordering the Right Amount
- Measure twice. Use a tape measure on every dimension. Eyeballing leads to costly surprises on pour day.
- Check your subgrade. Uneven ground means some areas will be thicker than planned. If your base varies by even half an inch, total volume increases significantly over a large slab.
- Add 5–10% for waste. Spillage, overfill, and form inconsistencies always consume more material than you expect.
- Round up, not down. Coming up short mid-pour risks cold joints, project delays, and a second delivery fee that far exceeds the cost of an extra quarter yard.
- Confirm the mix design. Standard residential work uses 3,000–3,500 PSI. Driveways and high-traffic areas benefit from 4,000 PSI or higher.
- Schedule ahead. Most concrete suppliers need 24–48 hours of advance notice for standard orders and longer for specialty mixes. During peak season (April through October), book early to lock in your delivery window.